Question - The Maxwell Corporation has a standard costing system in which variable manufacturing overhead is assigned to production on the basis of standard machine-hours. The following data are available for July:
- Actual variable manufacturing overhead cost incurred: $35,220
- Actual machine-hours worked: 1,200 hours
- Variable overhead rate variance: $4,020 Unfavorable
- Total variable overhead spending variance: $8,050 Unfavorable
The standard number of machine-hours allowed for July production is.