Question - A company expected its annual overhead costs to be $900,000 and direct labor costs to be $1,000,000. Actual overhead was $870,000, and actual labor costs totaled $1,100,000. How much is the company's predetermined overhead rate to the nearest cent?
a. $0.87
b. $0.79
c. $0.90
d. $0.82