Activity times for the project


Problem:

Activity Immediate Predecessor Time (days)

A - 3
B - 7
C A 4
D B 2
E- C,D 5
F - A 6
G - E,F 3

The following are activity times for the project. Find the earliest, latest, and slack times for each activity. Then Find the critical path.

Solution Preview :

Prepared by a verified Expert
Project Management: Activity times for the project
Reference No:- TGS01954105

Now Priced at $20 (50% Discount)

Recommended (93%)