Activity-on-Node Diagrams.
Chapter notes can be download link below.
Download link:
https://we.tl/0UmlQIfEMw
Homework Assignment:
Questions
1. Draw an Activity-on-Node Diagram for the following:
Activity Name Predecessor(s)
A None
B None
C A
D A,B
E B
F C,D,E
2. Draw an Activity-on-Node Diagram for the following:
Activity Name Predecessor(s)
A None
B None
C A
D A,B
E D
F E
G C
H F,G
3. Should the critical path activities be monitored differently from non-critical path activities for a project by a project manager? Explain your response.
4. Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:
Activity Name Predecessor(s) Duration (Weeks)
A None 5
B None 10
C A 10
D A,B 30
E D 10
F E 15
5. Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:
Activity Name Predecessor(s) Duration (Weeks)
A None 5
B None 10
C None 10
D A,B 5
E C 15
F C,D 10
G E,F 5
6. Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following:
Activity Name Predecessor(s) a m b
A None 5 30 40
B None 10 20 50
C None 5 15 30
D A 5 10 30
E B,C 15 20 25
F C,D 15 20 60
G F 10 20 50