Activity-on-node diagrams


Description:

Activity-on-Node Diagrams.

Chapter notes can be download link below.

Download link:

https://we.tl/0UmlQIfEMw

Homework Assignment:

Questions

1. Draw an Activity-on-Node Diagram for the following:

Activity Name    Predecessor(s)

A    None
B    None
C    A
D    A,B
E    B
F    C,D,E

2. Draw an Activity-on-Node Diagram for the following:

Activity Name    Predecessor(s)

A    None
B    None
C    A
D    A,B
E    D
F    E
G    C
H    F,G

3. Should the critical path activities be monitored differently from non-critical path activities for a project by a project manager?  Explain your response.

4. Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:

Activity Name    Predecessor(s)    Duration (Weeks)

A    None    5
B    None    10
C    A    10
D    A,B    30
E    D    10
F    E    15

5.  Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity,  and project critical path for the following:

Activity Name    Predecessor(s)    Duration (Weeks)

A    None    5
B    None    10
C    None    10
D    A,B    5
E    C    15
F    C,D    10
G    E,F    5

6. Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity,  project duration, and project critical path for the following:

Activity Name    Predecessor(s)    a    m    b

A    None    5    30    40
B    None    10    20    50
C    None    5    15    30
D    A    5    10    30
E    B,C    15    20    25
F    C,D    15    20    60
G    F    10    20    50