Abagail Corp. uses activity-based costing system with three activity cost pools. The following information is provided:

  • Costs: Wages and salaries $ 215,000
  • Depreciation 119,000
  • Utilities 111,000
  • Total $440,000
  • Activity Cost Pools
  • Assembly Setting Up Other
  • Wages and salaries 0.59 30% 10%
  • Depreciation 0.33 45% 20%
  • Utilities 0.28 40% 30%
  • How much total cost would be allocated to the Assembly activity cost pool?