"The Ace Bicycle Company expects to produce 8,000 bicycles this year. Currently Ace also makes the chains for its bicycles. Ace's accountant reports the following costs for making 8,000 chains.
Direct materials are $4.47 per chain.
Direct manufacturing cost is $2.23 per chain.
Variable manufacturing overhead (power and utilities) is $1.23 per chain.
Inspection, setup, and material costs are $3,500.
Leasing the machine for the chains is $4,900.
Administration for the facility, including taxes and insurance is $55,000.
Ace has received an offer from an outside vendor to supply chains for $12.62 per chain.
The costs for the machine lease are the payments Ace makes for renting the equipment used in making the chains. If Ace buys all of its chains from the outside vendor, it does not need this machine.
Ace will not need to pay the variable costs or the inspection and setup costs if it purchases chains from the outside vendor.
Assume that if Ace purchases the chains from the ouside supplier, the facility where the chains are currently made will remain idle. Should Ace accept the outside supplier's offer at the anticipated production (and sales) volume of 8,000 units or continue to produce the chains in house? Enter the cost ($) of the preferred option."