Problem:
A project has a unit price of $5,000, a variable cost per unit of $4,000, fixed costs of $17,000,000, and depreciation expense of $6,970,000.
Required:
Question: What is the accounting break-even quantity?
Note: Explain in detail and show all computations in proper way.