Activity based costing (ABC) has determined that the shipment setup costs should be accounted for at the batch-level of activities. ABC believes that the costs assigned to the shipment setup for the current period will be $440,000. ABC is estimating that there will be 400 shipments totalling 8,000 units during the current period. How much cost should be allocated to each shipment?