A workcell is being planned to produce a part at rate of 420 units.day, Suppose for planning purposes the company uses 7 hours as the normal workday. What is the required CT (take time) of the cell? Should the workcell be designed so that it has an actual CT longer or shorter than the required CT? Explain.