A work package for code implementation has release of a build as its completion milestone with a budget of 2,000 hours. The build includes 150 testable requirements. If the build was released with 120 requirements integrated, and actual cost of 1,800 hours, earned value would be:
A. 1,900 hrs
B. 1,800 hrs
C. 1,600 hrs
D. None of the above