A work center with fixed labor cost is scheduled to operate


A work center with fixed labor cost is scheduled to operate 800 hours per month. The work center could produce up to 35,000 units in 800 hours; however, demand averages 24,000 parts per month. Each setup takes 15 minutes (0.25 hours). Find the batch size that minimizes production lead time.