A work cell is required to make 200 computerized diagnostic


Question 1

A work cell is required to make 200 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours is available for productive work. What is takt time for this cell? (Please input the number in minutes)

Question 2

A work cell is required to make 80 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours are available for productive work. These assemblies require five operations, with times of 1.0, 1.8, 2.4, 2.5, and 1.4 minutes each. How many workers will be needed?