A work cell at Chris Ellis Commercial Laundry has a workstation with two machines, and each unit produced at the station needs to be processed by both of the machines. (The same unit cannot be worked on by both machines simultaneously.)
Each machine has a production capacity of 4 units per hour. What is the throughput time of the work cell?