1.The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14.
.png)
a. What is the project's duration if only normal times are used?
b. What is the minimum cost schedule?
c. What is the critical path for the minimum costschedule?