A new product's chief uncertainty is its annual net revenue. So far, $35,000 has been spent on development, but an additional $30,000 is required to finish development. The firm's interest rate is 10%.
(a) What is the expected PW for deciding whether to proceed?
(b) Find the P(loss) and the standard deviation for proceeding.