A vertical curve is designed for 90 km/h and has an initial grade of +2.5% and final grade of -1.0 %. the PVT is at station 3+480. It is known that a point on the curve at station 3+440 is at elevation 75m. What is the stationing and elevation of the PVC? What is the stationing and elevation of the high point on the curve?