A tree service works 10 hours per day, 6 days per week during the summer.The average number of jobs done per day is 2.5, which includes travel time, setup time, time trimming trees, and cleanup time.
What is the average processing time per job?
How many jobs can be done in a week?
Let us assume that the tree service on average receives 20 requests by customers for tree trimming jobs per week.
Can this tree service handle the work?Please explain the tree service’s situation.
What is the tree service’s situation if the tree service receives 12 requests by customers for tree trimming jobs per week? Please explain.