A transmission line project involving 51 towers has been approved. The number of engineering hours needed to accomplish the first detailed tower design is 124. Assuming a 93% learning curve,
a. what is your estimate of the number of engineering hours needed to design the seventh tower and to design the last tower in the project?
b. what is your estimate of the cumulative average hours required for the first five designs?