A time study analysis was observed a worker for 30 minutes. During that time the worker completed 42 parts. The analysts rated the worker as producing at 130 percent. The base rate of the worker is $5 per hour. The firm has established 15 percent as a fatigue and personal time allowance.
If the worker produced 500 units during an eight-hour day, what wages would the worker have earned?