A swimming pool company has 120,000 labor hours available per summer and with a labor productivity of 8 pools per 5,000 hours. a. How many pools can the company install this summer? b. Suppose the multifactor productivity was one pool per $30,000. How much should the company expect to spend this summer constructing the pools?