a steak house operates with 2 full time employees


A Steak House operates with 2 full time employees who work 8 hours per day plus a number of part-time employees who work 2 or 3 hour shifts during peak meal times. Management wants to develop a schedule for part time employees that will minimize labor costs and still provide customer service. The steak house is open from 11:00am until 10:00pm. Part-time employees are paid $7.60/hr. The total number of  employees needed for each hour is shown in the table below:

Time of Day

Total Employees

11 - Noon

9

Noon - 1pm

9

1pm - 2pm

9

2pm -3pm

3

3pm - 4pm

3

4pm - 5pm

3

5pm - 6pm

6

6pm - 7pm

12

7pm - 8pm

12

8pm - 9pm

7

9pm - 10pm

7

One full time employee comes on duty at 11:00 am, works 4 hours, takes a 1 hr break and works another 4 hrs. The second full time employee comes to work at 1pm and works the same 4-1-4 pattern.

Develop a minimum cost schedule (of start-times and 2hr and 3hr shift assignments) for the part-time employees? What is the daily labor expense for part-time employees?