A software manager is in charge of the development


A software manager is in charge of the development of a safety-critical software system, which is designed to control a radiotherapy machine to treat patients suffering from cancer. This system is embedded in the machine and must run on special-purpose with a fixed amount of memory (256 Mbytes). The machine communicates with a patient database system to obtain the details of the patient and, after treatment, automatically records the radiation does delivered and other treatment details in the database.
The COCOMO method is used to estimate the effort required to develop this system and an estimate if 26 person-month is computed. All cost driver multipliers were set to 10 when making this estimate.
Explain why this estimate should be adjusted to take project, personnel, product, and organizational factors into account. Suggest four factors that might have significant effects on the initial COCOMO estimate and propose possible values for these factors. Justify why you have included each factor.

Request for Solution File

Ask an Expert for Answer!!
Software Engineering: A software manager is in charge of the development
Reference No:- TGS0117360

Expected delivery within 24 Hours