A small renovation of a hard rock cafeacute gift shop has


Problem:

A Small renovation of a Hard Rock Café gift shop has six activities (in hours). For the following estimates of a, m, and b, calculates the expected time and the standard deviation of each activity:

Activity

a

m

B

A

11

15

19

B

27

31

41

C

18

18

18

D

8

13

19

E

17

18

20

F

16

19

22