A small assembly line for the assembly of power steering pumps needs to be balanced. Exhibit 8.11 in the text is the precedence diagram. The cycle time is determined to be 1.5 minutes. How would the line be balanced using a. longest (largest) processing time first rule? Station Tasks Total time Idle Time 1 2 3 Total