A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. Can they complete the project in the 38 class days remaining until the end of the semester? Identify the critical activities. Identify the non-critical activities and their relevant slack times
Activity Immediate Activity Time
Predecessors
A --- 3
B --- 5
C A, B 2
D C 6
E C 5
F E 3
G C 4
H D, G, F 3
I D, F 4
J H 2
K I, J 2
(a) Draw a project network for the above activities.
(b) Determine which activities are critical
(c) Determine which activities are non-critical and their respective slack times.
(d) How long will the project take to accomplish?