Question: A proposed nuclear power plant will cost $2.3 billion to build (today) and then will produce cash flows of $310 million a year for 5 years (year 1 to year 5). It then must be decommissioned at a cost of $910 million (in year 5). What is project NPV if the discount rate is 4%? The response must be typed, single spaced, must be in times new roman font (size 12) and must follow the APA format.