Question: A project will cost $180,000 The after-tax future cash flows are expected to be $50,000 annually for 7 years. Based on the above information, what is the project's DPB if the interest rate is 8%? The response must be typed, single spaced, must be in times new roman font (size 12) and must follow the APA format.