A project to build a new bridge seems to be going very well


A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 53% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,419,800 and it was done for only $1,299,800. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,499,800 but was actually done for $8,999,800. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,499,800. To date they have spent $4,999,800 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project to build a new bridge seems to be going very well
Reference No:- TGS01192806

Expected delivery within 24 Hours