A Project Manager works for XYZ company and acknowledges that there are some unknowns in her procurement statement of work and specifications. Which contract type should Daisy Duke not use?
A. Time and Materials.
B. Cost-plus incentive fee.
C. Fixed-Price Incentive.
D. Cost-Reimbursable.