Question: A project manager has just learned that the schedule performance index (SPI) for his project is 85 percent. The calculation of the cost performance index (CPI) is 107 percent. How would you describe this project both in terms of budget and schedule? The response must be typed, single spaced, must be in times new roman font (size 12) and must follow the APA format.