A project has two paths that you are concerned about the


A project has two paths that you are concerned about. The first path (which we will call #1) has an expected path time of 15 weeks and a standard deviation of 3. The second path (#2) has an expected path time of 14 weeks and a standard deviation of 3.4. Which path is critical if the project must be completed within 20 weeks?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project has two paths that you are concerned about the
Reference No:- TGS0976078

Expected delivery within 24 Hours