Question: A process is monitored using an X‾ chart with UCL = 13.8 and LCL = 8.2. The process standard deviation is estimated to be 6.6. If the X‾ chart is based on three-sigma limits,
a. What is the estimate of the process mean?
b. What is the size of each of the sampling subgroups?