A printing company has a contract with a legal firm to copy their court documents. Daily demand is a constant at 20000 pages to be copied.
The mean lead time for the contractor is 4 days with a standard deviation of 1.25 days for delivering copies. Find the reorder point for the law firm. Desired service level is 95%.