A printing company has a contract with a legal firm to copy their court documents. Daily demand is a constant at 25000 pages to be copied. The mean lead time for the contractor is 5 days with a standard deviation of 1.5 days for delivering copies. Find the reorder point for the law firm. Desired service level is 95%.