A particular workstation has a capacity of 1000 units per day and variability is moderate such that c2a +c2e/2= 1. Demand is currently 900 units per day. Suppose the management has decided that the cycle time should be no more than 1.5 times the raw process time (a) What is the current cycle time? (b) If variability does not change, what would the capacity have meet the CT and demand requirements? c If the capacity is not changed what value of V need to meet the CT and demand requirements?