A new bridge project is being evaluated at an interest rate of 7%. Reccomend an alternative based on the capitalized cost for each option below:
Option Construction Cost Annual O&M Life(years)
Concrete $ 18 million $250,000 50
Steel $ 25 million $500,000 70