A natural gas methane pipeline is to be designed to


A natural gas (methane) pipeline is to be designed to transport the gas at a rate of 50,000 scfm. The pipe is to be 6 in. ID, and the maximum pressure that the compressors can develop is 10,000 psig. The compressor stations are to be located in the pipeline at the point at which the pressure drops to 100 psi above that at which choked flow would occur (this is the section pressure for the compressors). if the design temperature for the pipeline is 60 F, the compressors are 60% efficient, and the compressor stations each operate with three stages and inter stage cooling to 60 F, determine ( a ) The proper distance between compressor stations, in miles. ( b ) The optimum inter stage pressure and compression ratio for each compressor stage. ( c ) The total horsepower required for each compressor station.

Request for Solution File

Ask an Expert for Answer!!
Mechanical Engineering: A natural gas methane pipeline is to be designed to
Reference No:- TGS0973457

Expected delivery within 24 Hours