A multi national company calculates the cost of capital of a project in country x. The risk free interest rate is 7.25%, and the risk-premium is 5.25%. The market return rate in country X is 22%. Beta coefficient for the project in country X is 1.2, and in home country is 1.4. Calculate the cost of capital for the project in country x.