1. WBS is:
A decomposition of the project into smaller more manageable components
List of schedule milestones
Detail of required resources
2. A more decomposed work breakdown structure (WBS) will result in:
Less estimating accuracy
Better control of the project
Lower status reporting costs
A greater likelihood that some key project element has been overlooked
3. The lowest level in the decomposition diagram or work breakdown structure (WBS) is: a.
Work packages
Subtasks
Tasks
Code of accounts
4. Progressive elaboration means:
Continuously improving and detailing a plan as more detailed information become available
Building the project plan in a collaborative team setting
A newer approach to project planning that include iterations and agile processes