A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results: Observation 1 2 3 4 5 Time (secs) 85 87 83 85 72 What is the standard time for this task if the employee worked at a 24 percent faster pace than average and an allowance of 18 percent of the workday is used? (Keep one decimal place in your answer)