A manufacturing company forecasts to sell 220 units in the month of November. As of October 25th, they have orders for 60 units the week of 11/2, 40 units the week of 11/9 and 17 units the week of 11/16. Safety stock is 5 units and the starting inventory is 70 units. What is the projected on hand in the week of 11/2?