A manager wants to estimate the remaining time that will be needed to complete a five-unit job. The initial unit of the job required 13 hours, and the work has a learning percentage of 77. Estimate the total time remaining to complete the job. (Round your intermediate calculations to 4 decimal places. Round your "Estimated time" and final answer to 2 decimal places.)
Total time remaining hours