A manager must decide between two machines the manager will


A manager must decide between two machines. The manager will take into account each machine’s operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 130 hours and a projected average repair time of 14 hours. Projected times for machine B are an average operating time of 66 hours and a repair time of 6 hours. What are the projected availabilities of each machine? Machine A Machine B