A manager must decide between two machines. The manager will take into account each machine’s operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 130 hours and a projected average repair time of 9 hours. Projected times for machine B are an average operating time of 52 hours and a repair time of 8 hours. What are the projected availabilities of each machine? (Round your answers to 3 decimal places.)
Availability
Machine A
Machine B