a machine shop has two machines m1 and m2 four


A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three hours on machine M2. Job B will take three hours on M1 and two hours on M2. Job C, takes seven hours on M1and three hours on M2. Job D, requires five hours on M1 and one hour on M2. Using Johnson's rule, in what order should these jobs be done? ABCD, ACDB etc.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: a machine shop has two machines m1 and m2 four
Reference No:- TGS0418812

Expected delivery within 24 Hours