A machine cell uses 192 pounds of a certain material each day. Material is transported in vats that hold 22 pounds each. Cycle time for the vats is about 1.50 hours. The manager has assigned an inefficiency factor of .07 to the cell. The plant operates on an eight-hour day.
How many vats will be used? (Round up your answer to the next whole number.)
Number of vats