A local municipality has issued a request for proposals to conduct a feasibility study to design, implement, and sustain a recycling program in a small town. As PM, you need to develop a bar chart to assign responsibility and maintain a project schedule. You develop the following activities, precedence relationships, durations, and responsible individuals:

Develop a bar chart to help you manage this project.