The Hickory Cabinet and Furniture Company produces sofas, tables, and chairs at its plant in Greensboro, North Carolina. The plant uses three main resources to make furniture - wood, upholstery, and labor. The resource requirements for each piece of furniture and the total resources available weekly are as follows:
|
Resource Requirements
|
|
Wood (board ft.)
|
Upholstery (yd.)
|
Labor (hr.)
|
Sofa
|
7
|
12
|
6
|
Table
|
5
|
--
|
9
|
Chair
|
4
|
7
|
5
|
Total available resources
|
2,250
|
1,000
|
240
|
|
|
|
|
The furniture is produced on a weekly basis and stored in a warehouse until the end of the week, when it is shipped out. The warehouse has a total capacity of 650 pieces of furniture. Each sofa earns $400 in profit, each table $275, and each chair, $190. The company wants to know how many pieces of each type of furniture to make per week to maximize profit.
a. Formulate a linear programming model for this problem
b. Solve the model by using the computer.