Question: A firm with a 10 percent cost of capital is considering a project for this year's capital budget. The project's expected after tax cash flows are as follows: Year: 0 1 2 3 4 Cash flow: -$5000 $2100 $2300 $2500 $2400
Calculate the project's profitability index (PI).