A firm uses a serial assembly system and needs answers to the following-
a. A desired output of 900 units per shift (7.5 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 30 seconds. What is the required cycle time for such a system?
b. How efficient is your system with the cycle time you calculated?